TEHRAN Sep. 13 (Shana)--Overhaul at gas processing plants of the country is going on with 76 percent physical progress in total, director of coordination and supervision on production at the National Iranian Gas Company (NIGC), Mehdi Jamshidi said.
Essential repairs at first, third, fourth and fifth gas processing plants of South Pars gas field as well as Hasheminejad and Ilam gas refineries are complete now, Jamshidi told Shana.
He said overhaul operations at Fajr Jam and Bidboland gas processing plants are underway with 49 and 80 percent physical progress respectively while physical progress at Sarkhon and Qeshm refineries has reached 55 percent.