SHANA -- Pars Oil and Gas Company (POGC) launched liquefied petroleum gas (LPG) storage tanks for stockpiling the item produced at phases 20 and 21 of the supergiant South Pars Gas Field in the Persian Gulf.
According to POGC, the facility was launched with the aim of completing the value-chain of the two phases.
Alireza Ebadi, operator of the ...
Shana-- Operator of SP20&21 project at the supergiant South Pars Gas Field said SP20 platform will come on-stream by next Saturday, March 18.
Alireza Ebadi told a group of visiting journalists on Tuesday that the pipe laying operations for the transfer of natural gas from SP20&21 to onshore refining facilities have finished, adding operating ...
Shana -- The operator of phases 20 and 21 of the supergiant South Pars Gas Field says phase 21's platform is currently recovering 27 million cubic meters of natural gas per day, saying the platform is faced with no restrictions in supplying gas to onshore refining facilities.
Alireza Ebadi said one third of the gas recovered from phase 21 is being ...
Shana Phase 21 of the supergiant South Pars Gas Field will become operational by late December once the sea pipeline of the project is laid for delivering sour gas from the phase to onshore refining facilities.
Speaking to Shana, operator of phases 20 and 21 of the gas field Alireza Ebadi said the platform of phase 21 will start gas production ...
TEHRAN, June 20 (Shana) -- The Loading operation of the phase 21 topside will start early next week from Khorramshahr Yard, operator of phases 20 and 21 said.
Alireza Ebadi told Shana that concluding operations over 11 wells at phase 21 are going on as planned and the phase's topside will be loaded from Khorramshahr Yard next week.
He ...
TEHRAN, Feb. 09 (MNA) The first gas sweetening unit of Phases 20 and 21 in South Pars field will begin preliminary operation in late March.
Project Director of Phases 20 and 21 at Pars Oil and Gas Company (POGC) Alireza Ebadi said all stages of preparation including testing of lines and connections for the refinery sector as well as all utility ...
TEHRAN (Tasnim) The construction of 20th and 21st development phases of the giant South Pars Gas Field has had near 85 percent of progress, and it is predicted that it would get fully operational next year, an executive official said on Tuesday.
The executive manager of the construction project, Alireza Ebadi, noted that all refinery units ...
Tehran, Aug 3, IRNA Phase 21 of the supergiant South Pars gas field is 78% complete and its gas, after being refined, will be injected to national gas trunklines by winter to boost supply during the cold, the project manager of the phase said.
Alireza Ebadi said phases 20&21 of the gas field are prioritized over other phases by Iranian petroleum ...