26 Apr 2024
Sunday 16 October 2016 - 16:08
Story Code : 235313

Last satellite platforms of phases 17&18 to be loaded soon

TEHRAN, Oct 16 (Shana) -- Operator of South Pars phases 17 and 18 development projects said the last satellite platforms of the two phases are scheduled to be loaded on October 18 at Bandar Abbas Industrial Yard.

Hassan Boveiri said Platform 17B, which weighs 2,300 tons, will be able to recover 500 million cubic feet of gas on a daily basis and transfers it to onshore refining facilities.

He said according to the plan, installation of the structure will wrap up on November 10 which will be the last step in development of the two phases.

He said the platform's construction is 92.3% complete and its pre-startup has made 66.32% progress.

Platform 17B is the 4th platform belonging to phases 17&18 of the supergiant South Pars Gas Field, and is being built by Iran Shipbuilding & Offshore Industries Complex Co. (ISOICO).

By SHANA
https://theiranproject.com/vdcgqn9xwak9ww4.5jra.html
Your Name
Your Email Address