Financial Tribune - The first gas unit of Dalahu Combined Cycle Power Plant in Eslamabad-e-Gharb County, Kermanshah Province, with a capacity of 310 megawatts came online on Monday.

According to the Energy Ministry news portal Paven, the plant will have another gas unit of 310 MW and a 290 MW steam unit, which together will boost nominal electricity production capacity to 910 MW.

“The second gas unit will come on stream in February and the steam unit will be operational next summer,” managing director of the Thermal Power Plants Holding Company said.