TEHRAN July 6 (Shana)--Iran’s Offshore Engineering and Construction Company’s (IOEC) finished laying gas pipelines to connect offshore to onshore facilities.
 Trench Dredging Industries Company (TDIC) as a civil engineering and maritime construction company and a subsidiary to IOEC completed an 860 meters pipe laying project in South Pars gas field phase 22 and will start similar operations in phase 23 soon.



After completion of these operations, executive works will start laying 113 kilometers of pipeline in phase 22.
 TDIC’s managing director Saeed Sadrzadeh said that shore-pull pipeline projects of South Pars gas field phases 22, 23 and 24 include two 4 and 32 inches gas pipeline carried out by domestic contractors.
The development plans of phases 22-24 aim at production of 56.6 million cubic meters of sour gas, 75 thousand barrels of gas condensate, 2.87 thousand tons of LPG (propane and butane), 2.74 thousand tons of ethane and 400 tons of sulfur per day.

By SHANA

 

The Iran Project is not responsible for the content of quoted articles.


Story Code: 105191

News Link :
https://www.theiranproject.com/en/news/105191/ioec-completes-pipe-laying-project

The Iran Project
  https://www.theiranproject.com